Closed distribution facility installation work
Start date: 2021.03.10
Approved date: Done
The foundations of the four main buildings of the anode cathode plant
Start date: 2020.02.12
Approved date: -
Electrical installation work inside buildings 101, 102 and 106
Start date: 2020.06.15
Approved date: Done
Construction of 0.4 kV power supply cable outside building 209
Start date: 2020.10.08
Approved date : Done
35kV Power transmission lines
Start date: 2022.03.15
Approved date: Done
10/0.4 kV power transmission lines
Start date: 2022.03.15
Approved date: Done
Cathode Copper Plant
Start date: 2021
Approved date: -